How much concrete do you need for a slab?

Multiply length × width × thickness in metres, then add 5 to 10%. A 4 m × 3 m slab, 10 cm thick, needs 1.2 m³ before the extra.

Published · 4 min · By the Convert & Calculate team

Try it: Concrete Volume

Open the full tool

Your details

Try an example

Units
Bag size

Result

Concrete volume

0.600 m³

0.78 cubic yards

Concrete weight
1,440 kg (1.44 t)
Bags needed (25 kg)
50
Your slab (plan view)
10 cm thick3 m2 m
Image

Good to know: A slab 3 m × 2 m × 10 cm needs 0.6 m³, about 1,440 kg of concrete.

How it was worked out · notes
  • Assumes 2,400 kg/m³. Buy 5–10% extra for uneven ground and spillage. Follow the mix guidance for your project.

Bags needed by bag size

Pre-mixed bags at their typical yield. Your bag size is highlighted. For larger jobs, ready-mix delivery is usually easier.

Bag sizeBagsWeight of bags
20 kg641,280 kg
25 kg501,250 kg
40 kg321,280 kg

The sum, step by step

Put every measurement into the same unit first. For the 4 m × 3 m slab, 10 cm becomes 0.1 m, so the volume is 4 × 3 × 0.1 = 1.200 m³. At the 2,400 kg per cubic metre the calculator assumes, that weighs 2,880 kg.

Then add your allowance for uneven ground and spillage. Adding 10% takes 1.2 m³ to 1.32 m³. The 5 to 10% range is a rule of thumb, so use the top of it when the ground is rough.

Common slab sizes

Volume and bags before any extra allowance
SlabVolumeWeight25 kg bags
3 m × 2 m × 10 cm0.600 m³1,440 kg50
4 m × 3 m × 10 cm1.200 m³2,880 kg100
5 m × 4 m × 15 cm3.000 m³7,200 kg250
10 ft × 10 ft × 4 in0.944 m³ (1.23 cubic yards)2,265 kg79

What changes the answer

  • Thickness. Volume rises in step with it, so going from 10 cm to 15 cm needs 50% more concrete. A 5 m × 4 m slab needs 2 m³ at 10 cm, and 3 m³ at 15 cm.
  • Uneven ground. Measure the depth in several places and use the average, not the shallowest point.
  • Bag yield. The calculator assumes a 25 kg bag makes 0.012 m³. Yield varies by product, so check the label and adjust.

Bags or ready-mix?

Compare the bag count with what you can realistically lift and mix. A 1.2 m³ slab means moving 100 bags and 2.88 tonnes by hand. Once that looks unrealistic, ask local suppliers about ready-mix delivery, including any minimum order and whether a truck can reach the site.

The easy mistake

Mixing units is the usual slip. Treating 4 inches as 0.4 ft, for example, gives 20% too much, because 4 inches is one third of a foot, or about 0.333 ft. Use the length converter if your tape and your plan disagree.

Please note: Estimates only. Measure your actual space, buy a little extra, and check product labels, safety requirements and local building rules. Do not rely on this for structural or safety-critical work.

Run your own numbers with the Concrete Volume tool.